MENU
Dickens Quality Demolition | Sub Zero

Sub Zero

Sub Zero is a large manufacturing facility that was built less than 10 years ago that underwent an extensive addition nearly doubling the size of the facility

Project Specific Challenges

Sub Zero presented many challenges. The existing structure had to be shored so that the exterior Tilt Panel walls could be detached and then removed in a safe fashion; each panel weighed over 100,000 pounds & had to be removed in their entirety. Holes were cut into the panels to allow access for new spread footings to be poured which made the job for DQD more technical during the pick sequence. All while the facility was active less than 30’ away separated by a framed partition

© Dickens Quality Demolition
All Rights Reserved